Construction Information

The table below shows a summary of the current construction activity in the District. Click on a dam to view detailed information about that dam's construction.

Construction Summary
Dam % Complete Construction Contract Scheduled Start Scheduled Completion Fiscal Year

Dam No. 9

100%

$305,000

Aug. 2003

Dec. 2003

2003 - 2004

Dam No. 11

100%

$854,698

Jan. 2005

Sept. 2005

2005

Dam No. 12

100%

$553,698

Dec. 2004

Aug. 2005

2005

Dam No. 13A

100%

$2,197,937

Sept. 2005

Dec. 2006

2005 - 2006

Dam No. 14

100%

$248,125

Feb. 2005

Sept. 2005

2005

EWS - Phase I

100%

$329,341

Dec. 2004

Sept. 2005

2005

Dam 1 - Phase 1

100%

$1,203,238

Nov. 2005

April 2006

2006-2007

Dam 6 - Phase 1

100%

$322,619

Nov. 2005

April 2006

2006-2007

Dam 15

100%

$533,040

Nov. 2006

June 2007

2007

Dam 20

100%

$348,100

Nov. 2006

June 2007

2007

Dam 1 - Phase II

62%

$382,285

Aug. 2007

May 2008

2007-2008

Dam 6 - Phase II

43%

$414,590

Sept. 2007

May 2008

2007-2008

Dam 17

 

$723,750

Dec. 2007

June 2008

2008

Dam 19

 

$637,690

Dec. 2007

June 2008

2008

EWS - Phase II

100%

$655,003

Nov. 2005

May 2007

2006

EWS - Phase III

100%

$873,208

Dec. 2006

Sept. 2007

2007

EWS - Phase IV

75%

$266,200

Dec. 2006

Ongoing

2007

 

 