Construction Information
The table below shows a summary of the current construction activity in the District. Click on a dam to view detailed information about that dam's construction.
Construction Summary
| Dam |
% Complete |
Construction Contract |
Scheduled Start |
Scheduled Completion |
Fiscal Year |
Dam No. 9 |
100% |
$305,000 |
Aug. 2003 |
Dec. 2003 |
2003 - 2004 |
Dam No. 11 |
100% |
$854,698 |
Jan. 2005 |
Sept. 2005 |
2005 |
Dam No. 12 |
100% |
$553,698 |
Dec. 2004 |
Aug. 2005 |
2005 |
Dam No. 13A |
100%
|
$2,197,937 |
Sept. 2005 |
Dec. 2006 |
2005 - 2006 |
Dam No. 14 |
100% |
$248,125 |
Feb. 2005 |
Sept. 2005 |
2005 |
EWS - Phase I |
100% |
$329,341 |
Dec. 2004 |
Sept. 2005 |
2005 |
Dam 1 - Phase 1 |
100% |
$1,203,238 |
Nov. 2005 |
April 2006 |
2006-2007 |
Dam 6 - Phase 1 |
100% |
$322,619 |
Nov. 2005 |
April 2006 |
2006-2007 |
Dam 15 |
100% |
$533,040 |
Nov. 2006 |
June 2007 |
2007 |
Dam 20 |
100% |
$348,100 |
Nov. 2006 |
June 2007 |
2007 |
Dam 1 - Phase II |
62% |
$382,285 |
Aug. 2007 |
May 2008 |
2007-2008 |
Dam 6 - Phase II |
43% |
$414,590 |
Sept. 2007 |
May 2008 |
2007-2008 |
Dam 17 |
|
$723,750 |
Dec. 2007 |
June 2008 |
2008 |
Dam 19 |
|
$637,690 |
Dec. 2007 |
June 2008 |
2008 |
EWS - Phase II |
100% |
$655,003 |
Nov. 2005 |
May 2007 |
2006 |
EWS - Phase III |
100% |
$873,208 |
Dec. 2006 |
Sept. 2007 |
2007 |
EWS - Phase IV |
75% |
$266,200 |
Dec. 2006 |
Ongoing |
2007 |
|
| This site Copyright © 2003-2008, Upper Brushy Creek Water Control and
Improvement District
Designed, developed, maintained and hosted by Freese and Nichols, Inc. Online
Services
Administrative Tools
|