The program is currently ahead of the original, projected 10-year schedule. As of January 2010, the flood monitoring systems have been installed and commissioned at all 21 high hazard dam sites and a public Web site has been established to provide current rainfall and reservoir level data (www.ubcwcid.org). As of April 2010, fourteen of the 21 high hazard dams have been upgraded to safely pass the 100% PMF, one dam is currently in construction, and design is underway for the next six modernization projects.

 

Dam Status Construction
Contract
Construction
Start
Construction
Completion
Contractor
Dam 9 Complete $305,000 Aug. 2003 Dec. 2003 Ranger Excavating
Dam 12 Complete $553,698 Dec. 2004 Aug. 2005 DayCo Const. Co.
EWS - Phase I Complete $329,341 Dec. 2004 Sept. 2005 C. Fowler and Assoc.
Dam 11 Complete $854,698 Jan. 2005 Sept. 2005 DayCo Const. Co.
Dam 14 Complete $248,125 Feb. 2005 Sept. 2005 C.C. Carlton Industries
Dam No. 13A Complete $2,197,937 Sep. 2005 Dec. 2006 Chasco Constructors
EWS - Phase II Complete $655,003 Nov. 2005 May. 2007 C. Fowler and Assoc.
Dam 1 - Phase I Complete $1,203,238 Nov. 2005 Apr. 2006 Keystone Construction
Dam 6 - Phase I Complete $322,619 Nov. 2005 Aug. 2006 Keystone Construction
Dam 15 Complete $533,040 Nov. 2006 Jun. 2007 Austin Engineering Co.
Dam 20 Complete $348,100 Nov. 2006 Jun. 2007 MAC, Inc.
EWS - Phase III Complete $873,208 Dec. 2006 Sep. 2007 Keystone Construction
EWS - Phase IV On Hold $266,200 Dec. 2006 TBD Keystone Construction
Dam 1 - Phase II Complete $382,285 Aug. 2007 Dec. 2007 Austin Filter Systems
Dam 6 - Phase II Complete $414,590 Sep. 2007 May. 2008 Mann Contractors, Ltd.
Dam 17 Complete $723,750 Dec. 2007 Sept. 2008 Austin Filter Systems
Dam 5 Complete $297,300 Aug. 2008 Dec. 2008 Austin Engineering Co.
Dam 2 Ongoing $443,200 Dec. 2008 Sept. 2009 Capital Concret Contractors
Dam 16 Ongoing $797,400 Dec. 2008 Sept. 2009 Capital Concret Contractors
Dam 19 Complete $637,690 Dec. 2007 Sept. 2008 Austin Filter Systems
Dam 14 Complete $279,025 Sept. 2009 April 2010 Patin Construction, LLC
Dam 4 Complete $289,385 Nov. 2009 May 2010 Ross Construction, Inc.